- Comprehensive National Drainage Development Study
- Feasibility Studies and Design Consultancy Services for Coastal Protection Works at Blanchisseuse, Matelot, Grande Riviere, San Souci and Toco (28th July 2008 – December 2010.
- North Oropouche River Basin Study (22nd May 2008 – November 2010).
- Ortoire River Basin Study
- National Programme Upgrade of Drainage Channels: In The Construction Phase
- Matura River Improvement Works – Construction of embankments, berms, grading of river and landscaping (11th November 2007 – 11th May 2008).
- Alley's Creek River Improvement Works – Construction of 680 m of reinforced concrete walls and 560 m of inverts (14th May 2008 – July 2010).
- Camacho Drain La Puerta – Construction of 120 m of reinforced concrete cantilever walls (22nd June 2009 – December 2010).
- Dibe River Rehabilitation Works – Construction of 115 m of reinforced concrete cantilever walls (22nd June 2009 – December 2010).
- Flood Mitigation & Erosion Control Programme
- Caroni River Improvement Works Phase 2 (Construction phase) – Construction of embankments, berms, and grading of river and landscaping (11th December 2007 – 11th December 2009).